Cybersecurity readinessWorking document

Project roadmap / November 2026 — March 2027

Sprint & pilot roadmap.

Practical cybersecurity education for everyday decisions. Built for people, supported by IT teams, shaped with our pilot partners.

Preparing people for risk.Helping IT teams train their users, with the goal of saving time and money and reducing risk.

01 / The road ahead

Three sprints. One shared goal.

Pilot deployment begins on 5 February 2027; first feedback is scheduled for 19 March 2027.

18 Nov — 18 Dec 2026

Sprint 01

Define the learning experience; round table on 17 December.

5 Jan — 5 Feb 2027

Sprint 02

Prototype and validate; begin pilot deployment on 5 February.

16 Feb — 19 Mar 2027

Sprint 03

Pilot First Feedback on 19 March.

19 March 2027

Pilot First Feedback

First feedback milestone at the end of Sprint 3.

02 / Sprint execution

Start small. Learn with purpose.

Validate the learning experience before building the pilot.

01

Sprint one

Define & listen

18 NOV — 18 DEC
2026

Align on audiences, priority risks and the smallest useful pilot experience.

What we do

  • Meet the SME and school contacts with the project manager.
  • Map learner needs and the IT sponsor's journey.
  • Select a scenario and define learning objectives.
  • Agree MVP access, reporting, privacy and review responsibilities.

What we deliver

  • Pilot brief reviewed with both groups.
  • Prioritised scenario and MVP criteria.
  • Content template and sources (Should).

Decision: Can one scenario work for both groups, or should the context differ?

02

Sprint two

Prototype & validate

5 JAN — 5 FEB
2027

Test one complete learning journey before committing to implementation.

What we do

  • Draft a plain-language lesson and fictional scenario.
  • Prototype feedback, progress and the facilitator view.
  • Define start, completion and retry rules.
  • Test with both groups and review content accuracy and safety.

What we deliver

  • First reviewed training module.
  • Feedback from the SME and school.
  • Prioritised MVP implementation backlog (Should).

Decision: Is the scenario relevant and clear enough to build?

03 / What we are building

Essential by design.

Informed by practical learning paths, inspired by Hack The Box.

The MVP

One complete learning loop

Participants access the right content, complete a relevant scenario and have progress recorded.

Appropriate accessSafe simulationProgressLightweight reporting

Initial focus: finance, suppliers and supply chains.

The course

Learn. Practise. Understand.

Short lessons and safe, controlled scenarios turn guidance into decisions.

PathLessonScenarioFeedbackProgress

Proposed first scenario: verify an urgent supplier payment change using an established channel.

The knowledge base

The team's source of truth

A shared, reviewed place for learning objectives, guidance, sources and content owners. The team uses it to create lessons and scenarios.

A searchable participant library is a possible later feature, not a pilot requirement.

04 / Validation & next steps

Grounded in real-world feedback.

Pilot partners

One SME. One school.

Both participant groups are confirmed. The project manager has the contacts and coordinates engagement.

Round table · 17 December

VELAR CYBERSECURITY

Discuss how Portugal can implement and enforce national cybersecurity legislation aligned with European Union requirements and shared European cybersecurity goals, including the roles of the CNCS, universities, social entities, companies and public authorities, as well as the implications for organisations and workforce readiness. Specific discussion topics are open to suggestions. Attendance, roles, venue and time remain to be confirmed.

After initial pilot feedback

Certification follows learning.

Company certification comes first, then customer certification, subject to applicable requirements. Consultant support is proposed, not decided.

People mentioned: Pedro, Dina, Dr. Gorge Gamboa (identified as director of Escola Profissional do Funda) and a local company manager. Names, roles and participation to be confirmed.

Sprint planning / Backlog

Work items & acceptance criteria.

Must items are essential; Should items are desirable.

Sprint 1 · 18 November–18 December 2026

Define the learning experience

Goal: Agree on the pilot audience, first scenario, learning objectives and MVP boundaries.

  • MustInterview the confirmed SME and school contacts

    Acceptance: PM arranges conversations; team records learner needs, relevant roles, constraints and expectations for each group.

  • MustDefine learner and sponsor journeys

    Acceptance: Document how a learner accesses and completes training, and what an IT sponsor or school facilitator needs to see.

  • MustSelect the first scenario

    Acceptance: SME and school contacts review the proposed supplier-payment scenario, or the team selects a better shared alternative.

  • MustDefine learning objectives

    Acceptance: Write 2–3 observable actions, such as recognising warning signs and choosing an independent verification process.

  • MustDefine MVP requirements

    Acceptance: Agree on content access, scenario completion, progress recording and a lightweight reporting view, including who can see what.

  • MustDefine pilot measurement and privacy needs

    Acceptance: Specify what to record, why it is needed, who can access it and how pilot feedback will be collected.

  • ShouldCreate the content template and source list

    Acceptance: Establish how authors, reviewers, sources and update dates will be recorded for each lesson and scenario.

  • ShouldDefine launch risks and assumptions

    Acceptance: Record risks around participant availability, content review, data protection and delivery capacity, with owners.

Sprint 2 · 5 January–5 February 2027

Prototype and validate

Goal: Test a complete training module and reporting concept with representative users before committing to implementation.

  • MustWrite the first lesson

    Acceptance: Plain-language draft covers the learning objectives, explains key terms and identifies a recommended verification process.

  • MustCreate the scenario

    Acceptance: Fictional message and payment details; learner makes a decision; each answer receives an explanation and a recommended next step.

  • MustPrototype the learner journey

    Acceptance: A user can navigate from assigned content to lesson, scenario, feedback and a completion screen—even if the prototype does not yet persist data.

  • MustPrototype the reporting view

    Acceptance: Facilitator can understand proposed fields for assigned, started and completed training; access is restricted by organisation or group in the design.

  • MustTest with representatives

    Acceptance: Walk at least one representative from each confirmed group through the prototype; record confusion, relevance and suggested improvements.

  • MustDefine progress-recording rules

    Acceptance: Specify what counts as started and completed, what happens on retry, and which events the MVP must persist.

  • MustReview scenario safety and content

    Acceptance: Use fictional data; no real payment action or contact with external parties; have a designated reviewer approve the draft.

  • ShouldPrepare implementation backlog

    Acceptance: Break the approved journey into build-ready stories for access, content, scenario interaction, progress and reporting.

05 / Delivery standards

Definition of Done & deadlines.

Sprint 1 ends 18 December 2026; Sprint 2 ends with pilot deployment beginning 5 February 2027.

Sprint 01 · deadline: 18 December 2026

Define the learning experience

Done when the following evidence is available:

  • SME and school contacts have been interviewed; their needs and constraints are documented.
  • Learner and IT sponsor or facilitator journeys are documented, including who can access what.
  • Both groups have reviewed the proposed supplier-payment scenario, or the team has selected a better shared alternative; 2–3 observable learning objectives are recorded.
  • MVP access, scenario completion, progress and reporting are agreed, including who can see what.
  • Measurement and privacy needs specify what to record, why, who can access it and how feedback will be collected.

Should: prepare the content template and source list; record launch risks, assumptions and owners.

Sprint 02 · deadline: 5 February 2027

Prototype and validate

Done when the following evidence is available:

  • A plain-language lesson covers the objectives, explains key terms and identifies a recommended verification process; each scenario answer receives an explanation and a recommended next step.
  • The prototype covers assigned content, lesson, scenario, feedback and completion; it need not persist data yet.
  • The facilitator view explains assigned, started and completed status and the intended group access restrictions.
  • At least one representative from each group has tested the prototype and feedback is recorded.
  • Start, completion and retry rules are documented; a designated reviewer approves content and scenario safety.
  • The scenario uses fictional data, with no real payment action or external contact.

Should: prepare a prioritised, build-ready implementation backlog.

06 / Next steps

From definition to pilot.

Actions are proposed; owners and intermediate dates remain to be agreed.

01 / Now

Confirm and schedule

Confirm team capacity and responsibilities. The project manager arranges conversations with the SME and school; agree content, product and security review ownership.

02 / Sprint 1 and 2

Define, then validate

Define the scenario in Sprint 1; test the prototype with both groups in Sprint 2 and document feedback. The 17 December round table can inform Sprint 1; its details remain to be confirmed.

03 / Before 5 February

Prepare for launch

Build and test the MVP, review content and data separation, prepare onboarding and support, and establish baseline measures and a feedback process.

Sprint 3 · 16 February–19 March 2027: Pilot First Feedback is scheduled for 19 March. Sprint 3 backlog and acceptance criteria are not yet defined.

Proposed pilot readiness: agreed scenarios work end to end; no unresolved critical security or tenant-isolation issues remain; participants understand data use and can access support. Certification remains out of scope until after initial pilot feedback.