Sprint 01
Define the learning experience; round table on 17 December.
Project roadmap / November 2026 — March 2027
Practical cybersecurity education for everyday decisions. Built for people, supported by IT teams, shaped with our pilot partners.
01 / The road ahead
Pilot deployment begins on 5 February 2027; first feedback is scheduled for 19 March 2027.
Define the learning experience; round table on 17 December.
Prototype and validate; begin pilot deployment on 5 February.
Pilot First Feedback on 19 March.
First feedback milestone at the end of Sprint 3.
02 / Sprint execution
Validate the learning experience before building the pilot.
Sprint one
18 NOV — 18 DEC
2026
Align on audiences, priority risks and the smallest useful pilot experience.
Decision: Can one scenario work for both groups, or should the context differ?
Sprint two
5 JAN — 5 FEB
2027
Test one complete learning journey before committing to implementation.
Decision: Is the scenario relevant and clear enough to build?
03 / What we are building
Informed by practical learning paths, inspired by Hack The Box.
Participants access the right content, complete a relevant scenario and have progress recorded.
Initial focus: finance, suppliers and supply chains.
Short lessons and safe, controlled scenarios turn guidance into decisions.
Proposed first scenario: verify an urgent supplier payment change using an established channel.
A shared, reviewed place for learning objectives, guidance, sources and content owners. The team uses it to create lessons and scenarios.
A searchable participant library is a possible later feature, not a pilot requirement.
04 / Validation & next steps
Pilot partners
Both participant groups are confirmed. The project manager has the contacts and coordinates engagement.
Round table · 17 December
Discuss how Portugal can implement and enforce national cybersecurity legislation aligned with European Union requirements and shared European cybersecurity goals, including the roles of the CNCS, universities, social entities, companies and public authorities, as well as the implications for organisations and workforce readiness. Specific discussion topics are open to suggestions. Attendance, roles, venue and time remain to be confirmed.
After initial pilot feedback
Company certification comes first, then customer certification, subject to applicable requirements. Consultant support is proposed, not decided.
Sprint planning / Backlog
Must items are essential; Should items are desirable.
Sprint 1 · 18 November–18 December 2026
Goal: Agree on the pilot audience, first scenario, learning objectives and MVP boundaries.
Acceptance: PM arranges conversations; team records learner needs, relevant roles, constraints and expectations for each group.
Acceptance: Document how a learner accesses and completes training, and what an IT sponsor or school facilitator needs to see.
Acceptance: SME and school contacts review the proposed supplier-payment scenario, or the team selects a better shared alternative.
Acceptance: Write 2–3 observable actions, such as recognising warning signs and choosing an independent verification process.
Acceptance: Agree on content access, scenario completion, progress recording and a lightweight reporting view, including who can see what.
Acceptance: Specify what to record, why it is needed, who can access it and how pilot feedback will be collected.
Acceptance: Establish how authors, reviewers, sources and update dates will be recorded for each lesson and scenario.
Acceptance: Record risks around participant availability, content review, data protection and delivery capacity, with owners.
Sprint 2 · 5 January–5 February 2027
Goal: Test a complete training module and reporting concept with representative users before committing to implementation.
Acceptance: Plain-language draft covers the learning objectives, explains key terms and identifies a recommended verification process.
Acceptance: Fictional message and payment details; learner makes a decision; each answer receives an explanation and a recommended next step.
Acceptance: A user can navigate from assigned content to lesson, scenario, feedback and a completion screen—even if the prototype does not yet persist data.
Acceptance: Facilitator can understand proposed fields for assigned, started and completed training; access is restricted by organisation or group in the design.
Acceptance: Walk at least one representative from each confirmed group through the prototype; record confusion, relevance and suggested improvements.
Acceptance: Specify what counts as started and completed, what happens on retry, and which events the MVP must persist.
Acceptance: Use fictional data; no real payment action or contact with external parties; have a designated reviewer approve the draft.
Acceptance: Break the approved journey into build-ready stories for access, content, scenario interaction, progress and reporting.
05 / Delivery standards
Sprint 1 ends 18 December 2026; Sprint 2 ends with pilot deployment beginning 5 February 2027.
Sprint 01 · deadline: 18 December 2026
Done when the following evidence is available:
Should: prepare the content template and source list; record launch risks, assumptions and owners.
Sprint 02 · deadline: 5 February 2027
Done when the following evidence is available:
Should: prepare a prioritised, build-ready implementation backlog.
06 / Next steps
Actions are proposed; owners and intermediate dates remain to be agreed.
01 / Now
Confirm team capacity and responsibilities. The project manager arranges conversations with the SME and school; agree content, product and security review ownership.
02 / Sprint 1 and 2
Define the scenario in Sprint 1; test the prototype with both groups in Sprint 2 and document feedback. The 17 December round table can inform Sprint 1; its details remain to be confirmed.
03 / Before 5 February
Build and test the MVP, review content and data separation, prepare onboarding and support, and establish baseline measures and a feedback process.
Sprint 3 · 16 February–19 March 2027: Pilot First Feedback is scheduled for 19 March. Sprint 3 backlog and acceptance criteria are not yet defined.
Proposed pilot readiness: agreed scenarios work end to end; no unresolved critical security or tenant-isolation issues remain; participants understand data use and can access support. Certification remains out of scope until after initial pilot feedback.